Gayaza House
Gayaza Road ยท started March 2026
Overall progress68%
Budget
UGX 210,000,000
Spent
UGX 142,800,000
Retention held
UGX 7,140,000
5% until defects clear
Milestones
- FoundationSigned off
- StructureSigned off
- RoofingSigned off
- ElectricalIn progress
- PlumbingNot started
- FinishingNot started
Material check
Cement (bags)
Short- Planned
- 420
- Ordered
- 380
- Delivered
- 360
- Used
- 344
- Remaining
- 16
Iron bars Y12
- Planned
- 260
- Ordered
- 260
- Delivered
- 260
- Used
- 258
- Remaining
- 2
Sand (trips)
Short- Planned
- 18
- Ordered
- 16
- Delivered
- 14
- Used
- 14
- Remaining
- 0
Bricks
Short- Planned
- 22,000
- Ordered
- 22,000
- Delivered
- 20,500
- Used
- 19,000
- Remaining
- 1,500
| Material | Planned | Ordered | Delivered | Used | Remaining |
|---|---|---|---|---|---|
| Cement (bags) Short | 420 | 380 | 360 | 344 | 16 |
| Iron bars Y12 | 260 | 260 | 260 | 258 | 2 |
| Sand (trips) Short | 18 | 16 | 14 | 14 | 0 |
| Bricks Short | 22,000 | 22,000 | 20,500 | 19,000 | 1,500 |